Earned Value Management Example: SPI, CPI, EAC Explained

Earned value explained with one simple example: PV, EV, AC, SPI, CPI and the EAC forecast, plus what each number tells a project manager.

What does an SPI of 1.0 mean?
The work is on schedule: earned value equals planned value.
Can CPI be above 1 and SPI below 1 at the same time?
Yes. The project can be under budget and behind schedule, for example when work is cheap because it is being delayed.
Which EAC formula is correct?
All three are correct for different assumptions. The question or the project facts tell you which assumption holds.

What earned value tells you

Earned value management compares three things: what you planned to have done, what you have actually done, and what it cost. With those, you can say whether the project is ahead or behind schedule, over or under budget, and what the final cost is likely to be. It is used in project management in general, and it appears in PMP® exam preparation because it connects numbers to decisions.

The example

A building has 10 identical floors to paint. The plan is one floor per week for 10 weeks, and the budget at completion (BAC) is 100,000, so each floor is planned at 10,000.

At the end of week 4:

  • Planned: 4 floors. Done: 3 floors.

  • Money spent so far: 35,000.

The three inputs

  • Planned value (PV): the value of the work planned to date. 4 floors x 10,000 = 40,000.

  • Earned value (EV): the planned value of the work actually done. 3 floors x 10,000 = 30,000.

  • Actual cost (AC): what you actually spent. 35,000.

A common mistake is to use the 35,000 as earned value. EV always uses the planned price of the finished work, not what it cost.

Variances and indexes

MeasureFormulaResultPlain words
Schedule variance (SV)EV minus PV30,000 minus 40,000 = minus 10,000Behind schedule by 10,000 of work
Schedule performance index (SPI)EV / PV30,000 / 40,000 = 0.75Producing 75 cents of planned work per planned dollar
Cost variance (CV)EV minus AC30,000 minus 35,000 = minus 5,000Over budget by 5,000 so far
Cost performance index (CPI)EV / AC30,000 / 35,000 = 0.86Getting 86 cents of value per dollar spent

Rule of thumb: a variance below zero or an index below 1 is unfavorable. Above is favorable.

Forecasting the final cost

Estimate at completion (EAC) depends on an assumption. Three common versions, using BAC = 100,000:

  1. The current cost trend continues: EAC = BAC / CPI = 100,000 / 0.857 = about 116,667.

  2. The overrun was a one-off and the rest goes to plan: EAC = AC + (BAC minus EV) = 35,000 + 70,000 = 105,000.

  3. Both cost and schedule performance affect the cost: EAC = AC + (BAC minus EV) / (CPI x SPI) = 35,000 + 70,000 / 0.643 = about 143,889.

  4. When the original estimate is no longer valid, the team makes a new bottom-up estimate of the remaining work (estimate to complete, ETC) and adds it to the actual cost: EAC = AC + bottom-up ETC.

Then:

  • Estimate to complete (ETC) = EAC minus AC. For version 1: 116,667 minus 35,000 = 81,667.

  • Variance at completion (VAC) = BAC minus EAC. For version 1: 100,000 minus 116,667 = minus 16,667.

  • To-complete performance index (TCPI) to reach the budget = (BAC minus EV) / (BAC minus AC) = 70,000 / 65,000 = 1.08. It says you must get 1.08 of value per dollar from now on to finish within budget.

In a question, the wording tells you which version applies: "at the current rate", "the variance was atypical", and so on. Read for the assumption before you pick a formula.

What a project manager does with this

The numbers do not decide anything alone. SPI 0.75 and CPI 0.86 say the project is late and costly; the next question is why. Is a supplier delayed, were estimates too optimistic, is the team short of people? The right response depends on the cause, which is why exam questions often ask for the next action rather than the number. See PMP mindset: 10 principles for situational questions, principle 5.

Practice

Try the earned value questions in the free PMP sample exam and read the explanations. For the other calculations in one place, see PMP Math Questions: The Calculations to Know.

Frequently asked questions

What does an SPI of 1.0 mean?The work is on schedule: earned value equals planned value.

Can CPI be above 1 and SPI below 1 at the same time?Yes. The project can be under budget and behind schedule, for example when work is cheap because it is being delayed.

Which EAC formula is correct?All three are correct for different assumptions. The question or the project facts tell you which assumption holds.

  • ELPMP.com home
  • All products
  • Simulator overview
  • How the modes work
  • Free sample exam
  • Exam guide
  • Help and FAQ
  • For Teams
  • Partners
  • About
  • Contact
  • Blog

ELPMP.com: hello@elpmp.com, support@elpmp.com, WhatsApp +1 (302) 887-2020