What the critical path is
The critical path is the longest sequence of dependent activities in a project schedule. It sets the shortest time in which the project can finish. A delay on any activity on that path delays the whole project, unless something else changes. Activities off the path have float: time they can slip without moving the end date.
The example
Six activities, durations in days:
| Activity | Duration | Starts after |
|---|---|---|
| A | 3 | none |
| B | 4 | A |
| C | 2 | A |
| D | 5 | B |
| E | 3 | C |
| F | 2 | D and E |
Step 1: list the paths
A, B, D, F: 3 + 4 + 5 + 2 = 14 days
A, C, E, F: 3 + 2 + 3 + 2 = 10 days
The longest path is A, B, D, F. That is the critical path, and the project takes 14 days.
Step 2: forward pass (earliest start and finish)
Early finish = early start + duration. An activity with several predecessors starts when the last of them finishes.
| Activity | Early start | Early finish |
|---|---|---|
| A | 0 | 3 |
| B | 3 | 7 |
| C | 3 | 5 |
| D | 7 | 12 |
| E | 5 | 8 |
| F | 12 | 14 |
F starts at 12, not 8, because it must wait for D.
Step 3: backward pass (latest start and finish)
Start from the project end (14) and subtract. Late start = late finish minus duration. When an activity feeds several successors, its late finish is the earliest of their late starts.
| Activity | Late finish | Late start |
|---|---|---|
| F | 14 | 12 |
| D | 12 | 7 |
| E | 12 | 9 |
| B | 7 | 3 |
| C | 9 | 7 |
| A | 3 | 0 |
For A, the late finish is 3, the earlier of B's late start (3) and C's late start (7).
Step 4: float
Total float = late start minus early start.
| Activity | Float |
|---|---|
| A | 0 |
| B | 0 |
| D | 0 |
| F | 0 |
| C | 7 minus 3 = 4 |
| E | 9 minus 5 = 4 |
The activities with zero float are exactly the critical path: A, B, D, F. C and E can slip by 4 days in total before they threaten the end date. Note that the 4 days are shared by C and E: if C uses all 4, E has none left.
What changes if you shorten an activity
Shortening D by 1 day (crashing, for example by adding people) makes the path A, B, D, F take 13 days, and the project ends in 13. Shortening C by 1 day changes nothing, because C is not on the critical path. This is why schedule compression targets the critical path first. Fast tracking means doing activities in parallel that were planned in sequence. Both add risk or cost, so they are a decision, not a default.
If you shorten D by 4 days, both paths take 10 days and both become critical. Always recheck after compressing.
Common mistakes
Adding durations of activities that run in parallel.
Forgetting that an activity waits for its slowest predecessor.
Assuming there is only one critical path. Several paths can tie.
Treating float as free time. It is a buffer, and using it leaves less for the next risk.
Practice
Schedule questions often combine a diagram with a question about delay or compression. Try the free PMP sample exam and read the explanations. For the other calculations, see PMP Math Questions: The Calculations to Know and Earned Value Simplified.
Frequently asked questions
Can a project have more than one critical path?Yes, when two or more paths have the same longest length. Then a delay on any of them delays the project.
Is the critical path the most important activities?No. It is the longest path in time, not the most valuable work. Important work can have float.
What is free float?The time an activity can slip without delaying the early start of its successor. In the example, E has a free float of 4, because F starts at 12 and E finishes at 8.